[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893769":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893769,580,1,"单选题","根据《标准施工招标文件》（2007 年版）通用合同条款，下列引起承包人索赔的事件中，只能获得工期补偿的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","发包人提前向承包人提供材料和工程设备",false,{"key":16,"text":17,"correct":14},"B","工程暂停后因发包人原因导致无法按时复工",{"key":19,"text":20,"correct":14},"C","因发包人原因导致工程试运行失败",{"key":22,"text":23,"correct":24},"D","异常恶劣的气候条件导致工期延误",true,"异常恶劣的气候条件导致工期延误是属于不可抗力，只索赔工期。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]