[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893768":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893768,580,1,"单选题","关于法规变化类合同价款的调整，下列说法正确的是（ ）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不实行招标的工程，一般以施工合同签订前的第42天为基准日",false,{"key":16,"text":17,"correct":14},"B","基准日之前国家颁布的法规对合同价款有影晌的，应予调整",{"key":19,"text":20,"correct":21},"C","基准日之后国家政策对材料价格的影响，如已包含在物价波动调价公式中，不再予以考虑",true,{"key":23,"text":24,"correct":14},"D","承包人原因导致的工期延误期间，国家政策变化引起工程造价变化的.合同价款不予调整","对于不实行招标的建设工程，一般以建设工程施工合同签订前的第 28 天作为基准日，A错；基准日之前国家颁布的法规对合同价款有影响的，承包人承担，B 错误；承包人原因导致的工期延误期间，国家政策变化引起工程造价增加的，合同价款不予调整，D 错误。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]