[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893764":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893764,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），当实际增加的工程量超过清单工程量 15％以上，且造成按总价方式计价的措施项目发生变化的，应将（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","综合单价调高，措施项目费调增",false,{"key":16,"text":17,"correct":14},"B","综合单价调高，措施项目费调减",{"key":19,"text":20,"correct":21},"C","综合单价调低，措施项目费调增",true,{"key":23,"text":24,"correct":14},"D","综合单价调低，措施项目费调减","综合单价的调整原则为：当工程量增加 15%以上时，其增加部分的工程量的综合单价应予调低；当工程量减少 15%以上时，减少后剩余部分的工程量的综合单价应予调高。工程量增加的，措施项目费调增；工程量减少的，措施项目费调减。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]