[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893762":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893762,580,1,"单选题","发包人应当依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的（ ），超过的，应在招标文件中明示增加赶工费用。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","5%",false,{"key":16,"text":17,"correct":14},"B","10%",{"key":19,"text":20,"correct":21},"C","20%",true,{"key":23,"text":24,"correct":14},"D","30%","本题考查的是合同价款调整。发包人应当依据相关工程的工期定额合理计算工期，压缩的工期天数不得超过定额工期的20%，超过的应在招标文件中明示增加赶工费用 。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]