[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893758":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893758,580,1,"单选题","某工程合同实施过程中发生了变更事件，在已标价清单中没有适用也没有类似单价，且工程造价管理机构发布的信息价格也缺价，承包人根据变更工程资料、计量规则、计价办法和有合法依据的市场价格计算出变更工程项目的价格为10万元，已知该项目发承包阶段招标控制价为1000万元，中标价为900万元(招标控制价和中标价中均包含20万元的安全文明施工费)，则该变更工程项目确认的变更价格应为（ ）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","9．00",false,{"key":16,"text":17,"correct":14},"B","8．98",{"key":19,"text":20,"correct":21},"C","10．00",true,{"key":23,"text":24,"correct":14},"D","9．80","已标价工程量清单中没有适用也没有类似于变更工程项目，且工程造价管理机构发布的信息（参考）价格缺价的，由承包人根据变更工程资料、计量规则、计价办法和通过市场调查等有合法依据的市场价格提出变更工程项目的单价或总价，报发包人确认后调整。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]