[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893752":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893752,580,1,"单选题","每个支付期末，承包人应与进度款同期向发包人提交本期间所有（ ）记录的签证汇总表，以说明本期间自己认为有权得到的相应金额。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计日工",true,{"key":16,"text":17,"correct":18},"B","暂估价",false,{"key":20,"text":21,"correct":18},"C","暂列金额",{"key":23,"text":24,"correct":18},"D","总承包服务费","本题考查的是工程变更类合同价款调整事项。每个支付期末，承包人应与进度款同期向发包人提交本期间所有计日工记录的签证汇总表，以说明本期间自己认为有权得到的计日工金额，调整合同价款，列入进度款支付。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]