[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893746":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893746,580,1,"单选题","2013年3月完成的某工程，按基准日期的价格计算工程进度款为200万元，合同支付中不能调值的部分占合同总价的20％；相关成本要素除水泥价格上涨15％外，其余均未发生变化，水泥费用在合同总价中所占的比重系数为0.3。按调值公式计算2013年3月实际工程结算款应为（）万元。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","200.00",false,{"key":16,"text":17,"correct":14},"B","207.20",{"key":19,"text":20,"correct":21},"C","209.00",true,{"key":23,"text":24,"correct":14},"D","230.00","P=200（0.2＋0.3×115／100＋0.5×100／100）=209.0",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]