[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893737,580,1,"单选题","在计算预算定额人工工日消耗量时，包含在人工幅度差内的用工是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","超运距用工",false,{"key":16,"text":17,"correct":14},"B","材料加工用工",{"key":19,"text":20,"correct":14},"C","机械土方工程的配合用工",{"key":22,"text":23,"correct":24},"D","工种交叉作业相互影响的停歇用工",true,"人工幅度差，即预算定额与劳动定额的差额，主要是指在劳动定额中未包括，而在正常施工情况下不可避免但又很难准确计量的用工和各种工时损失。内容包括：（1）各工种间的工序搭接及交叉作业相互配合或影响所发生的停歇用工。（2）施工过程中，移动临时水电线路而造成的影响工人操作的时间。（3）工程质量检查和隐蔽工程验收工作而影响工人操作的时间。（4）同一现场内单位工程之间因操作地点转移而影响工人操作的时间。（5）工序交接时对前一工序不可避免的修整用工。（6）施工中不可避免的其他零星用工。主要是各工序的交接。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]