[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893731":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893731,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB50500—2013），分部分项工程量清单中所列工程量以形成工程实体为准，按（ ）计算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","施工方案计算出来的数值",false,{"key":16,"text":17,"correct":14},"B","实际完成的全部工程量",{"key":19,"text":20,"correct":21},"C","工程完成后的净值",true,{"key":23,"text":24,"correct":14},"D","工程实体量与损耗量之和","分部分项工程量清单中所列工程量应按规定的工程量计算规则计算。《建设工程工程量清单计价规范》（GB50500—2013）明确了清单项目的工程量计算规则，其实质是以形成工程实体为准，并以完成后的净值来计算的。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]