[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893729":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893729,580,1,"单选题","下列费用中，应列入其他项目清单的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","专业工程暂估价",true,{"key":16,"text":17,"correct":18},"B","安全文明施工费",false,{"key":20,"text":21,"correct":18},"C","二次搬运费",{"key":23,"text":24,"correct":18},"D","夜间施工增加费","其他项目清单是指分部分项工程项目清单、措施项目清单所包含的内容以外，因招标人的特殊要求而发生的与拟建工程有关的其他费用项目和相应数量的清单。其内容包括暂列金额、暂估价、计日工和总承包服务费。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]