[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893725":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893725,580,1,"单选题","在同一合同段的工程量清单中，多个单位工程中具有相同项目特征的项目编码和计量单位时（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目编码不一致，计量单位不一致",false,{"key":16,"text":17,"correct":14},"B","项目编码一致，计量单位一致",{"key":19,"text":20,"correct":21},"C","项目编码不一致，计量单位一致",true,{"key":23,"text":24,"correct":14},"D","项目编码一致，计量单位不一致","同一招标工程的项目编码不得有重码，在同一个建设项目（或标段、合同段）中，有多个单位工程的相同项目计量单位必须保持一致。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]