[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893721":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893721,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500-2013）关于招标工程量清单中暂列金额的编制，下列说法正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","应详列其项目名称、计量单位，不列明金额",false,{"key":16,"text":17,"correct":14},"B","应列明暂定金额总额，不详列项目名称",{"key":19,"text":20,"correct":21},"C","不同专业预留的暂列金额应分别列项",true,{"key":23,"text":24,"correct":14},"D","没有特殊要求一般不列暂列金额","暂列金额由招标人填写其项目名称、计量单位、暂定金额等，若不能详列，也可只列暂定金额总额。不同专业预留的暂列金额应分别列项,故选 C。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]