[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893720":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893720,580,1,"单选题","《建设工程工程量清单计价规范》规定，分部分项工程量清单项目编码的第四级为表示（ ）的顺序码。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分项工程",true,{"key":16,"text":17,"correct":18},"B","附录分类",false,{"key":20,"text":21,"correct":18},"C","分部工程",{"key":23,"text":24,"correct":18},"D","专业工程","本题考查的是土建工程工程量清单的编制方法。各级编码代表的含义：（1）一级：表示专业工程代码，两位；（2）二级：表示附录分类顺序码，两位；（3）三级：表示分部工程顺序码，两位；（4）四级：表示分项工程项目名称顺序码，三位；（5）五级：表示清单项目名称顺序编码，三位。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]