[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893719":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893719,580,1,"单选题","除另有说明外，分部分项工程量清单表中的工程量应等于（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","实体工程量",true,{"key":16,"text":17,"correct":18},"B","实体工程量+施工损耗量",false,{"key":20,"text":21,"correct":18},"C","实体工程量+施工需要增加的工程量",{"key":23,"text":24,"correct":18},"D","实体工程量+措施工程量","本题考查的是土建工程工程量清单的编制方法。除另有说明外，所有清单项目的工程量应以实体工程量为准，并以完成后的净值计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]