[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893711":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893711,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500—2013），允许投标人根据具体情况对招标工程量清单进行修正或增加的内容是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","分部分项工程量清单",false,{"key":16,"text":17,"correct":18},"B","措施项目清单",true,{"key":20,"text":21,"correct":14},"C","暂列金额",{"key":23,"text":24,"correct":14},"D","计日工","措施项目的内容应依据招标人提供的措施项目清单和投标人投标时拟定的施工组织设计或施工方案确定，故 B 正确。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]