[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893710":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893710,580,1,"单选题","编制工程量清单出现计算规范附录中未包括的清单项目时，下列正确的做法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","补充项目编码由附录顺序码与B和三位阿拉伯数字组成",false,{"key":16,"text":17,"correct":18},"B","补充项目应报省级工程造价管理机构备案",true,{"key":20,"text":21,"correct":14},"C","补充项目的工作内容可不明确",{"key":23,"text":24,"correct":14},"D","补充项目编码由编制人根据需要自主确定","本题考查的是土建工程工程量清单的编制方法。附录中没有的项目，编制人应作补充：（1）补充项目的编码必须按本规范的规定进行：工程量计算规范的代码+B+3位阿拉伯数字，从001起顺序编制，不得重码（9个计算规范，01、02……09）；（2）工程量清单中应附补充项目的项目名称、项目特征、计量单位、工程量计算规则和工作内容；（3）将编制的补充项目报省级或行业工程造价管理机构备案，比如补充房屋建筑与装饰工程，编码从01B001开始顺序编。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]