[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893709":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893709,580,1,"单选题","下列措施项目中，应按分部分项工程量清单编制方式编制的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","垂直运输",true,{"key":16,"text":17,"correct":18},"B","安全文明施工",false,{"key":20,"text":21,"correct":18},"C","二次搬运",{"key":23,"text":24,"correct":18},"D","冬雨季施工","本题考查的是土建工程工程量清单的编制方法。有些措施项目是可以计算工程量的项目，如脚手架工程，混凝土模板及支架（撑），垂直运输，超高施工增加，大型机械设备进出场及安拆，施工排水、降水等，这类措施项目按照分部分项工程量清单的方式采用综合单价计价。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]