[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893706":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893706,580,1,"单选题","根据《建设工程工程量清单计价规范》（GB 50500－2013），关于计日工，下列说法中正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计日工表包括各种人工，不应包括材料、施工机械",false,{"key":16,"text":17,"correct":18},"B","计日工按综合单价计价，投标时应计入投标总价",true,{"key":20,"text":21,"correct":14},"C","计日工表中的项目名称由招标人填写，工程数量由投标人填写",{"key":23,"text":24,"correct":14},"D","计日工单价由投标人自主确定，并按计日工表中所列数量结算","本题考查的是土建工程工程量清单的编制方法。选项A错误，计日工表包括人工、材料、施工机具；选项C错误，计日工表项目名称、暂定金额由招标人填写；选出D错误，投标时，单价由投标人自主报价，按暂定数量计算合价计入投标总价中。结算时，按发承包双方确认的实际数量计算合价。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]