[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893705":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893705,580,1,"单选题","根据《工程工程量清单计价规范》GB50500--2013，下列关于计日工的说法中正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","招标工程量清单计日工数量为暂定，计日工费不计入投标总价",false,{"key":16,"text":17,"correct":14},"B","招标时计日工单价由招标人根据实际情况暂定",{"key":19,"text":20,"correct":21},"C","计日工表应列出项目名称、计量单位和暂估数量",true,{"key":23,"text":24,"correct":14},"D","计日工金额不列入期中支付，在竣工结算时一并支付","本题考查的是工程变更类合同价款调整事项。选项A错误，招标工程量清单计日工数量为暂定，计日工费计入投标总价；选项B错误，招标时，计日工单价由投标人自主报价；选项D错误，每个支付期末，承包人应与进度款同期向发包人提交本期间所有计日工记录的签证汇总表，以说明本期间自己认为有权得到的计日工金额，调整合同价款，列入进度款支付。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]