[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893704":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893704,580,1,"单选题","关于招标控制价及其编制的说法，正确的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","综合单价中包括应由招标人承担的风险费用",false,{"key":16,"text":17,"correct":14},"B","计日工的单价由招标人根据实际情况填写",{"key":19,"text":20,"correct":21},"C","总承包服务费项目名称、服务内容由招标人填写，编制招标控制价时，费率及金额由招标人按有关计价规定确定",true,{"key":23,"text":24,"correct":14},"D","招标文件提供暂估价的主要材料，其主材费用应计入其他项目清单费用","选项A错误，正确的说法是综合单价中应包括招标文件中要求投标人所承担的风险内容及其范围（幅度）产生的风险费用；选项B错误，正确的说法是计日工项目名称、暂定数量由招标人填写。 选项C正确。 选项D错误，正确的说法是材料（工程设备）暂估单价进入清单项目综合单价，其他项目清单不汇总;",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]