[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893696":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893696,580,1,"单选题","当同一标段的一份工程量清单中含有多个单位工程且工程量清单是以单位工程为编制对象时，在编制工程量清单时应特别注意对项目编码（ ）位的设置不得有重码。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","一至三",false,{"key":16,"text":17,"correct":14},"B","四至六",{"key":19,"text":20,"correct":14},"C","七至九",{"key":22,"text":23,"correct":24},"D","十至十二",true,"当同一标段（或合同段）的一份工程量清单中含有多个单位工程且工程量清单是以单位工程为编制对象时，在编制工程量清单时应特别注意对项目编码10至12位的设置不得有重码的规定。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]