[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893652":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893652,580,1,"单选题","对某建筑地基设计要求强夯处理，处理范围为40.0×56.0m，需要铺设400mm厚土工合成材料，并进行机械压实，根据《房屋建筑与装饰工程工程量计算规范》（GB 50854—2013）规定，正确的项目列项或工程量计算是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","铺设土工合成材料的工程量为896m3",false,{"key":16,"text":17,"correct":18},"B","铺设土工合成材料的工程量为2240m2",true,{"key":20,"text":21,"correct":14},"C","强夯地基工程量按一般土方项目列项",{"key":23,"text":24,"correct":14},"D","强夯地基工程量为896m3","换填垫层，按设计图示尺寸以体积“m3”计算。铺设土工合成材料，按设计图示尺寸以面积“m2”计算。预压地基、强夯地基，按设计图示处理范围以面积“m2”计算。振冲密实（不填料），按设计图示处理范围以面积“m2”计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]