[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893648":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893648,580,1,"单选题","根据《房屋建筑与装饰工程工程量计量规范》（GB 50854—2013），关于土石方回填工程量计算，说法正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","回填土方项目特征应包括填方来源及运距",true,{"key":16,"text":17,"correct":18},"B","室内回填应扣除间隔墙所占体积",false,{"key":20,"text":21,"correct":18},"C","场地回填按设计回填尺寸以面积计算",{"key":23,"text":24,"correct":18},"D","基础回填不扣除基本垫层所占体积","回填土方项目特征包括密实度要求、填方材料品种、填方粒径要求、填方来源及运距。回填方工程量计算按设计图示尺寸以体积计算，具体规则如下：①室内回填。主墙间净面积乘以回填厚度，不扣除间隔墙。②场地回填。回填面积乘以平均回填厚度。③基础回填，挖方清单项目工程量减去自然地坪以下埋设的基础体积（包括基础垫层及其他构筑物）。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]