[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893640,580,1,"单选题","某建筑首层面积 500㎡，场地较为平整，其自然地面标高为+87.5m，设计室外地面标高为+87.15m，则其场地土方清单列项和工程量分别是（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按平整场地列项：500㎡",false,{"key":16,"text":17,"correct":14},"B","按一般土方列项：500㎡",{"key":19,"text":20,"correct":14},"C","按平整场地列项：175m3",{"key":22,"text":23,"correct":24},"D","按一般土方列项：175m3",true,"建筑物场地厚度≤±300mm的挖、填、运、找平，应按平整场地项目编码列项。厚度>±300mm的竖向布置挖土或山坡切土应按一般土方项目编码列项。挖一般土方按设计图示尺寸以体积计算。500×（87.5-87.15）=175m3。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]