[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893639":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893639,580,1,"单选题","某管沟工程，设计管底垫层宽度为 2000mm，开挖深度为 2.00m，管径为 1200mm，工作面宽为 400mm，管道中心线长为 180m，管沟土方工程量计量正确的为（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","432m3",false,{"key":16,"text":17,"correct":14},"B","576m3",{"key":19,"text":20,"correct":21},"C","720m3",true,{"key":23,"text":24,"correct":14},"D","1008m3","管沟土方以“m”计量，按设计图示以管道中心线长度计算。以“m”计量，按设计图示3管底垫层面积乘以挖土深度计算。无管底垫层按管外径的水平投影面积乘以挖土深度计算。不扣除各类井的长度，井的土方并入。管沟土方工程计量=2×180×2=720m3。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]