[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893637":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893637,580,1,"单选题","根据《房屋建筑与装饰工程工程量计量规范》（GB50854-2013），若开挖设计长为20m，宽为 6m，深度为 0.8m的土方工程，在清单中列项应为（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","平整场地",false,{"key":16,"text":17,"correct":18},"B","挖沟槽",true,{"key":20,"text":21,"correct":14},"C","挖基坑",{"key":23,"text":24,"correct":14},"D","挖一般土方","沟槽、基坑、一般土方的划分为：底宽≤7m，底长>3倍底宽为沟槽；底长≤3倍底宽、底面积≤l50m2为基坑；超出上述范围则为一般土方。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]