[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893634,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013）规定，关于桩基础的项目列项或工程量计算正确的为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","预制钢筋混凝土管桩试验桩应在工程量清单中单独列项",true,{"key":16,"text":17,"correct":18},"B","预制钢筋混凝土方桩试验桩工程量应并入预制钢筋混凝土方桩项目",false,{"key":20,"text":21,"correct":18},"C","现场截凿桩头工程量不单独列项，并入桩工程量计算",{"key":23,"text":24,"correct":18},"D","挖孔桩土方按设计桩长（包括桩尖）以米计算","打试验桩和打斜桩应按相应项目单独列项。截（凿）桩头以立方米计量，按设计桩截面乘以桩头长度以体积计算；以根计量，按设计图示数量计算。挖孔桩土（石）方按设计图示尺寸（含护壁）截面积乘以挖孔深度以体积计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]