[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893632":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893632,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013）规定，关于现浇混凝土基础的项目列项或工程量计算正确的为（）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","箱式满堂基础中的墙按现浇混凝土墙列项",true,{"key":16,"text":17,"correct":18},"B","箱式满堂基础中的梁按满堂基础列项",false,{"key":20,"text":21,"correct":18},"C","框架式设备基础的基础部分按现浇混凝土墙列项",{"key":23,"text":24,"correct":18},"D","框架式设备基础的柱和梁按设备基础列项","箱式满堂基础及框架式设备基础中柱、梁、墙、板按现浇混凝土柱、梁、墙、板分别编码列项；箱式满堂基础底板按满堂基础项目列项，框架设备基础的基础部分按设备基础列项。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]