[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893631":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893631,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB50854-2013），关于现浇混凝土梁工程量计算的说法，正确的是（）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","圈梁区分不同断面按设计中心线长度计算",false,{"key":16,"text":17,"correct":14},"B","过梁工程不单独计算，并入墙体工程量计算",{"key":19,"text":20,"correct":21},"C","异形梁按设计图示尺寸以体积计算",true,{"key":23,"text":24,"correct":14},"D","拱形梁按设计拱形轴线长度计算","圈梁、过梁、拱形梁按设计图示尺寸以体积计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]