[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893623,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013）规定，关于现浇混凝土柱的工程量计算正确的是（ ）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","有梁板的柱按设计图示截面积乘以柱基以上表面或楼板上表面至上一层楼板底面之间的高度以体积计算",false,{"key":16,"text":17,"correct":18},"B","无梁板的柱按设计图示截面积乘以柱基以上表面或楼板上表面至柱帽下表面之间的高度及体积计算",true,{"key":20,"text":21,"correct":14},"C","框架柱按柱基上表面至柱顶高度以米计算",{"key":23,"text":24,"correct":14},"D","构造柱按设计柱高以米计算","A 选项为楼板顶面；CD 选项应按体积计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]