[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893622,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB 50854-2013），现浇混凝土墙工程量应（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","扣除突出墙面部分体积",false,{"key":16,"text":17,"correct":14},"B","不扣除面积为0.33㎡孔洞体积",{"key":19,"text":20,"correct":21},"C","将伸入墙內的梁头计入",true,{"key":23,"text":24,"correct":14},"D","扣除预埋铁件体积","凸出墙面的垛并入墙体；大于0.3 占位要扣除；铁件不扣。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]