[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893613,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》（GB\u002FT50854-2013），某建筑物场地土方工程，设计基础长 27m，宽为 8m，周边开挖深度均为 2m，实际开挖后场地内堆土量为 570m3，则土方工程量为（）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","平整场地216m3",false,{"key":16,"text":17,"correct":14},"B","沟槽土方655m3",{"key":19,"text":20,"correct":14},"C","基坑土方528m3",{"key":22,"text":23,"correct":24},"D","一般土方438m3",true,"（1）建筑物场地厚度≤士 300mm的挖、填、运、找平，应按平整场地项目编码列项。厚度>±300mm的竖向布置挖土或山坡切土应按一般土方项目编码列项。（2）沟槽、基坑、一般土方的划分为：底宽≤7m，底长>3倍底宽为沟槽；底长≤3倍底宽、底面积≤150m2为基坑；超出上述范围则为一般土方。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]