[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893609":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893609,580,1,"单选题","挖土方的工程量按设计图示尺寸以体积计算，此处的体积是指（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","虚方体积",false,{"key":16,"text":17,"correct":14},"B","夯实后体积",{"key":19,"text":20,"correct":14},"C","松填体积",{"key":22,"text":23,"correct":24},"D","天然密实体积",true,"本题考查的是房屋建筑与装饰工程工程量的计算规则与方法。土方体积应按挖掘前的天然密实体积计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]