[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893608":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893608,580,1,"单选题","根据《建筑工程工程量清单计价规范》，下列基础土方的工程量计算，正确的（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","基础设计底面积×基础埋深",false,{"key":16,"text":17,"correct":14},"B","基础设计底面积×基础设计高度",{"key":19,"text":20,"correct":21},"C","基础垫层设计底面积×挖土深度埋深",true,{"key":23,"text":24,"correct":14},"D","基础垫层设计底面积×基础设计高度和垫层厚度之和","本题考查的是房屋建筑与装饰工程工程量的计算规则与方法。挖沟槽土方、挖基坑土方工程量按设计图示尺寸以基础垫层底面积乘以挖土深度计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]