[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893607":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893607,580,1,"单选题","下列关于地基处理与边坡支护工程，工程量清单计算规则，表述错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","砂石桩工程量，可按设计图示以数量计算",true,{"key":16,"text":17,"correct":18},"B","深层搅拌桩工程量，按设计图示尺寸的桩长以米计算",false,{"key":20,"text":21,"correct":18},"C","铺设土工合成材料工程量按设计图示尺寸以面积计算",{"key":23,"text":24,"correct":18},"D","振冲密实（不填料）地基的工程量均按设计图示处理范围以面积计算","本题考查的是房屋建筑与装饰工程工程量的计算规则与方法。砂石桩工程量，可按设计图示尺寸的桩长（包括桩尖）以米计算，或按设计桩截面乘以桩长（包括桩尖）以体积计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]