[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893581":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893581,580,1,"单选题","某建筑基础有100根钻孔灌注桩，设计桩长4.8m，断面直径为300mm，则总工程量为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","33.91m3",true,{"key":16,"text":17,"correct":18},"B","35.68m3",false,{"key":20,"text":21,"correct":18},"C","37.44m3",{"key":23,"text":24,"correct":18},"D","135.65m3","本题考查的是房屋建筑与装饰工程工程量的计算规则与方法。V＝π×r2×h×n＝π×（0.3\u002F2）2×4.8×100＝33.91（m3）。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]