[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893572":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893572,580,1,"单选题","现浇混凝土挑檐、雨篷与圈梁连接时，其工程量计算的分界线应为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","圈梁外边线",true,{"key":16,"text":17,"correct":18},"B","圈梁内边线",false,{"key":20,"text":21,"correct":18},"C","外墙外边线",{"key":23,"text":24,"correct":18},"D","板内边线","本题考查的是。现浇挑檐、天沟板、雨篷、阳台与板（包括屋面板、褛板）连接时，以外墙外边线为分界线；与圈梁（包括其他梁）连接时，以梁外边线为分界线。外边线以外为挑檐、天沟、雨篷或阳台。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]