[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893561":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},893561,580,1,"单选题","根据《建设工程工程量清单计价规范》的有关规定，工程量清单计算时，附墙柱侧面抹灰（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","不计算工程量，在综合单价中考虑",false,{"key":16,"text":17,"correct":14},"B","计算工程量后并入柱面抹灰工程量",{"key":19,"text":20,"correct":21},"C","计算工程量后并入墙面抹灰工程量",true,{"key":23,"text":24,"correct":14},"D","计算工程量后并入零星抹灰工程量","本题考查的是房屋建筑与装饰工程工程量的计算规则与方法。附墙柱、梁、垛、烟囱侧壁并入相应的墙面面积内。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]