[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893555":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893555,580,1,"单选题","编制钢筋工程量清单时，适宜采用暂估量加签证处理的钢筋是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","支撑双层钢筋用的“铁马”",true,{"key":16,"text":17,"correct":18},"B","伸出构件的锚固钢筋",false,{"key":20,"text":21,"correct":18},"C","设计注明的搭接钢筋",{"key":23,"text":24,"correct":18},"D","规范规定的搭接钢筋","本题考查的是招标工程量清单的编制。支撑钢筋（铁马）工程量按钢筋长度乘单位理论质量计算。如果设计未明确，其工程数量可为暂估量，结算时按现场签证数量计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]