[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893551":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893551,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013规定，关于石方的项目列项或工程量计算正确的为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","山坡凿石按一般石方列项",true,{"key":16,"text":17,"correct":18},"B","考虑石方运输，石方体积需折算为虚方体积计算",false,{"key":20,"text":21,"correct":18},"C","管沟石方均按一般石方列项",{"key":23,"text":24,"correct":18},"D","基坑底面积超过120m2的按一般石方列项","本题考查的是土石方工程。按设计图示尺寸以体积计算，单位：m3。当挖土厚度大于±300mm的竖向布置挖石或山坡凿石应按挖一般石方项目编码列项。沟槽、基坑、一般石方的划分为：底宽≤7m且底长>3倍底宽为沟槽；底长≤3倍底宽且底面积≤150m2为基坑；超出上述范围则为一般石方。挖石应按自然地面测量标高至设计地坪标高的平均厚度确定。管沟石方按设计图示以管道中心线长度计算，单位：m；或按设计图示截面积乘以长度以体积计算，单位：m3。有管沟设计时，平均深度以沟垫层底面标高至交付施工场地标高计算；无管沟设计时，直埋管深度应按管底外表面标高至交付施工场地标高的平均高度计算。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]