[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893548":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893548,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB 50854—2013，某建筑物外墙外边线的尺寸为60m×15m，其平整场地的清单工程量为（ ）m2。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","900",true,{"key":16,"text":17,"correct":18},"B","1054",false,{"key":20,"text":21,"correct":18},"C","1216",{"key":23,"text":24,"correct":18},"D","1350","根据《房屋建筑与装饰工程工程量计算规范》GB 50854—2013，平整场地的计算规则是按设计图示尺寸以建筑物首层面积计算，单位：m2。60*15=900m2",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]