[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893518":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893518,580,1,"单选题","根据《房屋建筑与装饰工程工程量计算规范》GB50854—2013，保温柱的工程量计算正确的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","按设计图示尺寸以体积计算",false,{"key":16,"text":17,"correct":14},"B","按设计图示尺寸以保温层外边线展开长度乘以其高度计算",{"key":19,"text":20,"correct":14},"C","按图示尺寸以柱面积计算",{"key":22,"text":23,"correct":24},"D","按设计图示尺寸以保温层中心线展开长度乘以其高度计算",true,"本题考查的是保温、隔热、防腐工程。保温柱、梁按设计图示尺寸以面积计算，柱按设计图示柱断面保温层中心线展开长度乘保温层高度以面积计算，扣除面积大于0．3m2梁所占面积。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]