[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893509":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893509,580,1,"单选题","某建筑工程挖土方工程量需要通过现场签证核定，已知用斗容量为1．5m3的轮胎式装载机运土500车，则挖土工程量应为（ ）m3。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","501．92",false,{"key":16,"text":17,"correct":18},"B","576．92",true,{"key":20,"text":21,"correct":14},"C","623．15",{"key":23,"text":24,"correct":14},"D","750","本题考查的是土石方工程。土方体积应按挖掘前的天然密实体积计算，如需按天然密实体积折算时，应按下图系数计算。挖土工程量=1．5×500／1．3=576．92（m3）。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]