[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893438":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893438,580,1,"单选题","对于国家投资的项目，施工图的建筑面积不得超过初步设计的（ ），否则必须重新报批。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","2％",false,{"key":16,"text":17,"correct":14},"B","3％",{"key":19,"text":20,"correct":14},"C","4％",{"key":22,"text":23,"correct":24},"D","5％",true,"本题考查的是建筑面积的作用。根据项目立项批准文件所核准的建筑面积，是初步设计的重要控制指标。对于国家投资的项目，施工图的建筑面积不得超过初步设计的5%，否则必须重新报批。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]