[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893398":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893398,580,1,"单选题","编制施工组织总设计涉及下列工作：①施工总平面图设计；②拟定施工方案；③编制施工总进度计划；④编制资源需求计划；⑤计算主要工种的工程量。正确的编制程序是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","⑤→①→②→③→④",false,{"key":16,"text":17,"correct":14},"B","①→⑤→②→③→④",{"key":19,"text":20,"correct":14},"C","①→②→③→④→⑤",{"key":22,"text":23,"correct":24},"D","⑤→②→③→④→①",true,"施工组织总设计的编制通常采用如下程序：①收集和熟悉编制施工组织总设计所需的有关资料和图纸，进行项目特点和施工条件的调查研究；②计算主要工种工程的工程量；③确定施工的总体部署；④拟订施工方案；⑤编制施工总进度计划；⑥编制资源需求量计划；⑦编制施工准备工作计划；⑧施工总平面图设计；⑨计算主要技术经济指标。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]