[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893396,580,1,"单选题","下列施工组织设计内容中，应当首先确定的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","施工平面图设计",false,{"key":16,"text":17,"correct":14},"B","机具设备需求计划",{"key":19,"text":20,"correct":14},"C","施工进度计划",{"key":22,"text":23,"correct":24},"D","施工方案",true,"施工组织设计的内容要结合工程对象的实际特点、施工条件和技术水平进行综合考虑，一般包括以下基本内容：①工程概况；②施工部署及施工方案；③施工进度计划；④施工平面图；⑤主要技术经济指标。首先应该确定施工方案。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]