[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893395":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893395,580,1,"单选题","需要编制单位工程施工组织设计的工程项目是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","工厂整体搬迁工程",false,{"key":16,"text":17,"correct":14},"B","新建居民小区工程",{"key":19,"text":20,"correct":14},"C","拆除工程定向爆破工程",{"key":22,"text":23,"correct":24},"D","发电厂干灰库烟囱工程",true,"施工组织设计按编制对象和范围不同可划分为三类：施工组织总设计、单位工程施工组织设计和分部分项工程施工组织设计。单位工程施工组织设计是以单位工程为编制对象，用来指导其施工全过程各项活动的技术、经济的局部性、指导性文件。故选D项。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]