[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893389":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},893389,580,1,"单选题","单位工程施工平面图设计的主要依据是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程概况和施工方案",false,{"key":16,"text":17,"correct":18},"B","施工方案和施工进度计划",true,{"key":20,"text":21,"correct":14},"C","施工进度计划和资源需求计划",{"key":23,"text":24,"correct":14},"D","资源需求计划和材料半成品堆放场地","本题考查的是单位工程施工组织设计。单位工程施工现场平面图应根据施工方案和施工进度计划的要求进行设计。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]