[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893384":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},893384,580,1,"单选题","在单层工业厂房结构吊装中，如安装支座表面高度为15.0m（从停机面算起），绑扎点至所吊构件底面距离0.8m部，索具高度为3.0m，则起重机起重高度至少为（ ）m。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","18.2",false,{"key":16,"text":17,"correct":14},"B","18.5",{"key":19,"text":20,"correct":14},"C","18.8",{"key":22,"text":23,"correct":24},"D","19.1",true,"起重机的起重高度必须满足所吊构件的吊装高度要求，对于吊装单层厂房应满足：H≥h1＋h2＋h3＋h4＝15.0＋0.3＋0.8＋3.0＝19.1（m）。式中，H为起重机的起重高度（m），从停机面算起至吊钩中心；h1为安装支座表面高度（m），从停机面算起；h2为安装空隙，一般不小于0.3m；h3为绑扎点至所吊构件底面的距离（m）；h4为索具高度（m），自绑扎点至吊钩中心，视具体情况而定。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]