[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-893365":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},893365,580,1,"单选题","静力压桩正确的施工工艺流程是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","定位→吊桩→对中→压桩→接桩→压桩→送桩→切割桩头",true,{"key":16,"text":17,"correct":18},"B","吊桩→定位→对中→压桩→送桩→压桩→接桩→切割桩头",false,{"key":20,"text":21,"correct":18},"C","对中→吊桩→插桩→送桩→静压→接桩→压桩→切割桩头",{"key":23,"text":24,"correct":18},"D","吊桩→定位→压桩→送桩→接桩→压桩→切割桩头","静力压桩由于受设备行程的限制，在一般情况下是分段预制、分段压入、逐段压入、逐段接长，其施工工艺顺序为：测量定位→压桩机就位→吊桩、插桩→桩身对中调制→静压沉桩→接桩→再静压沉桩→送桩→终止压桩→切割桩头。当第一节桩压入土中，其上端距地面0.5～1.0m左右时，将第二节桩接上，继续压入。",{"id":6,"name":27,"category":28,"favorite":29},"[土木建筑工程]建设工程计量与计价实务","建筑工程",0]